1. Permit-required confined space means a confined space that does not contain any physical hazards or any actual or potential atmospheric hazards capable of causing death or serious physical harm.
True
False
2. The word safety can be interpreted in many different ways. To some it can mean to be free from injury, to others it means to be secure from danger. These are both good definitions, but the one WSDOT likes best is _______?
The giving of life.
The giving of First aid.
The giving of protection.
The giving of Hard hats.
3. Which of the following is not surveying equipment?
Clinometer
Automatic level
Umbrella sun shade
None of the above
4. The use of a _________ in the recording of field terrain information requires attention to standard survey practices to ensure accuracy.
Data controller
Data interpreter
Digital controller
None of the above
5. To establish where the Public Lands Survey System (PLSS) lines intersected the boundary line, auxiliary corners were set, known as _____________?
Public corners
Witness corners
Government corners
none of the above
6. What is H in the following figure?
Highway Surveying Manual
Ellipsoidal height
Geoid height
Orthometric height(elevation)
None of the above
7. Random errors do not follow any fixed relationship to conditions or circumstances of the observation.
True
False
8. Which of the following is not a GPS survey method?
Static GPS Surveys
Fast-Static GPS Surveys
Fast-dynamic GPS Surveys
Kinematic GPS Surveys
9. A loop is a series of at least ________ independent, connecting base lines that start and end at the same station.
Two
Three
Four
Five
10. Survey specifications describe the methods and procedures needed to attain the desired survey standard and TSS is a Survey Specification method. What does TSS stand for?
Total Survey System
Time Specific System
Total Station System
None of the above
11. ___________ are a series of permanent points of known elevation located within the limits of the project.
Benchmarks
Trademarks
Accessmarks
None of the above
12. Point of compound curvature – Point common to two curves in the same direction with different radii.
True
False
13. ________ surveys are used for reconnaissance, location design, PS&E, and construction projects. They are used for mapping, digital terrain modeling, cross sectioning, and alignment determination.
Photogrammetric
Photographic
Graphic
None of the above
14. Prior to initiating a Control Survey a thorough search and recovery of existing horizontal and vertical control monuments in the immediate area of the project is required.
True
False
15. The _______ is an engineer who leads the Project Development Team and is responsible for overall project planning and completion.
Project Scheduler
Project Director
Project Manager
Project Supervisor
16. ________ is a trial and error process of finding the point where the slope intercepts the natural ground. This point is referred to as the "catch point" or "slope catch."
Slope staking
Point staking
Point catching
None of the above
17. A _________ is an opening (usually a pipe) in the embankment that allows water to pass from one side to the other.
Sewer
Culvert
Vent
Drain
18. Monuments can be divided into ______ groups.
Two
Three
Four
Five
19. ________ is the process of establishing a physical survey control network, consisting of survey markers representing specific points or corners and generally assigned with geographical coordinates and/or elevations, which pertain to a defined datum of reference.
Documentation
Monumentation
Photographic survey
Photometric survey
20. The purpose of the _________ is to provide cost estimates for survey labor, documentation (mapping) and monumentation for a specific project.
Preliminary land survey
Monument survey
Documentation survey